Other Facts about the Building

 
Financing:

Construction was financed by a $109.5 million bond measure approved by San Francisco voters in 1988. Construction of the Main Library cost $104.5 million.

The remaining funds were used for branch renovations. Furnishing, interior finishes and equipment were financed through $30 million in private funds raised by the Library Foundation of San Francisco.

Site:

Marshall Square in San Francisco Civic Center. The site is bounded by Larkin, Fulton, Hyde and Grove Streets

Chronology and Schedule:

1974: The Library Commission, the Friends of the San Francisco Public Library, Keep Libraries Alive!, and other citizen groups fight successfully to retain Marshall Square as the site for a new main library.

1985: The Friends of the San Francisco Public Library offers to work with Mayor Dianne Feinstein on the completion of the Civic Center, including use of Marshall Square for a new library.

1986: A task force is created by Mayor Feinstein to complete the design of the Civic Center.

A report by Becker and Hayes/Omni-Group criticizes the Old Main and calls for building a new library in Marshall Square.

The Friends of the San Francisco Public Library inaugurate a private fund-raising campaign for the New Main.

The Library Foundation of San Francisco is established to support a New Main.

(Friends & Foundation of the San Francisco Public Library.)

1987: A second study by Becker and Hayes/Omni-Group underscores the use of Marshall Square for a new library. Another study, by Skidmore Owings Merrill, recommends that the Old Main be used for a museum. (Future of the Old Main.)

The mayor calls for a new main library in Marshall Square as part of a Civic Center master plan.

1988: Library bond for 109.5 million passes for renovation of a few branches and construction of a new 376,000 square foot Main Library.

1989: Pei Cobb Freed & Partners of New York and Simon Martin-Vegue Winkelstein Moris of San Francisco are hired by the Library Commission as architects for the New Main.

1991: The Library Foundation officially announces its campaign for the New Main.

1992: Groundbreaking ceremony is held in Marshall Square.

Special Gifts campaign is launched to seek funds from various local constituencies (affinity groups) for particular collections and capital gains.

1993: On March 15, construction of the New Main begins.

1994: Topping-out ceremony marks the completion of the framing of the new building.

The Library Foundation reaches $30 million fund-raising goal and keeps going.

1995: New Main is completed. By the end of the year, the Library Foundation has raised $35 million.

1996: Opening of the Main is on April 18.

2000: Post Occupancy Evaluation Report (POE): Executive Summary

Seating:

Seating Capacity: 2,043 (5 times that of the Old Main Library)
Public Service Areas: 1,180 (3 times that of the Old Main Library)
Meeting Rooms: 544 seats
Auditorium: 235 seats
Study Rooms: 46 seats (2 in each study room)

Size:

Square Feet: 376,000. Six floors above ground. One floor below ground.

Footer color stripe
Have a question?
Contact Us  |   Frequently Asked Questions  |   Ask a Librarian  |   Search Our Site
Privacy Policy · Copyright © 2002-08 by San Francisco Public Library. All rights reserved. · Internet Use Policy

Last Modified: June 20, 2008

Valid XHTML 1.0!