Reference copies of the San Francisco Public Library Post Occupancy Evalution Final Report, dated January 4, 2000, are available at each branch library and at the Main Library in the Government Information Center. There are also two copies that can be checked out in the Government Information Center. Copies for review are also available in the Office of the Library Commission Secretary and the City Librarian at the Main Library in the Civic Center.
The Executive Summary of one report is posted on the library website. The Library Commission will hold a study session of the Post Occupancy Evaluation on Wednesday, February 16, 2000, at 5:30pm in the Koret Auditorium at the Main Library in the Civic Center.
Executive Summary
Introduction
The Post Occupancy Evaluation (POE) of the San Francisco Public Library was
recommended by a Strategic Audit commissioned by the Mayor, which was completed
in April, 1997 a year after the building was opened to the public in April, 1996.
At the time the POE was commissioned in January, 1999, the administrative team
members responsible for the design and construction of the facility had been
entirely replaced. The new administrative team views the POE as an opportunity to
obtain a baseline report by a group of outside experts to determine how public
services could be improved by changes to the facilities. The direction given to
the consultants was to evaluate the "here and now" of the library’s operation,
so that cost and value of making change could be considered by all levels of the
organization.
The current administration maintains allegiance to policies and decisions made by
the former administration only in so far as those decisions allow effective service
to be provided. The new administration has made a number of incremental changes,
however they have waited for the POE to provide an overview of changes that needed
to be considered.
The consultant team consisted of Cynthia Ripley, a principal of Ripley Architects,
who directed the study, and is recognized for the design of new and renovated library
buildings. The team included both library and technical consultants. The two library
consultants have extensive professional credentials; Florence Mason is a former
librarian, professor who specializes in facility and management consulting. Susan Kent,
in addition to her consulting practice, is the current director of the Los Angles
Public Library.
Purpose of the Study
The purpose of the study recommended by the Strategic Audit and described in the RFP
was very broad, but was clearly directed at the relationship between operations and
the facility. Since its opening, the building has been well respected as a piece of
civic architecture, but it has met with negative criticism with regard to accommodating
the typical library functions of a large central city library.
The goals and objectives for the study were stated in the original Request for Proposal
as follows:
- Provide an objective, empirical assessment of the performance of the New Main Library;
- Identify problems with the library facility and propose solutions to those problems;
- Prioritize recommended changes and improvements so that the library may deliver the highest level of service to the largest number of patrons, or those most critically affected by a particular issue;
- Provide information about the cost of any proposed changes, as well as a cost benefit analysis;
- Assist the library in prioritizing improvements;
- Provide the Library with objective information about the strengths and weaknesses of the library facilities so that the library building can better meet the needs of the public and library staff;
- Contribute to the published literature on library design guidelines in order to help San Francisco as well as other cities when they plan new libraries.
Modified POE Study Scope
In undertaking the study, the consultant team was disposed to focus first on library
operations, and then to see if the facility needed to be changed to improve them.
They recognized that management policies need to be evaluated as well as facilities,
but this was not the subject of the study. The consultants approached the task with
a sense of the importance of remaining independent both from individuals responsible
for the design and construction of the building and the many critics of the library.
The team was familiar with the capital investment in the facility and the prestige
of the architectural design team. The consultant team has not interacted with the
Commission or library administration to devise a way to implement change; this is
left to the library. Rather, the consultants have tried to frame the study as "a
review by outside experts" and set of recommendations, which the library can adopt
or develop. The POE Report is intended to assist those who support and love the
library to make positive change as all great and vital institutions must.
After the initial background investigation, the consultants concluded that operational
problems were severe enough to warrant change and that public services could be improved
by renovating interior areas of the facility. The consultants' perspective was a long
term one. The building is going to be in use for a long time—perhaps a 100 years or more.
Change may be needed now, and it will probably be needed every 10-15 years. As one of the
important centers for information for the city of San Francisco, the library will have to
keep pace with the appetite for information that characterizes our age.
After the initial reconnaissance, and with the approval of the Library Administration,
the consultants more closely defined the study objectives to focus on an investigation
of the following issues:
- Discovering the extent to which the existing collection was accommodated in the existing building, and the means to increase space for future collection growth;
- Examining means of improving public access to materials in the library;
- Investigating methods of improving the public’s ability to obtain services from staff or use of equipment;
- Assessing methods to improve the functional aspects of the building in terms of materials handling and operations affecting both staff and the public.
It should be noted that management issues are not the object of this
study, the consultants realize that facilities and management are closely related. They
recommend that San Francisco Public Library utilize this study and others to produce a
Master Plan which would define the organization, the services, the collection, technology,
staffing, and facilities for the library system. The library is completing a Strategic
Plan that includes some of these elements, however a total concept for San Francisco
Library services has yet to emerge as a blueprint for the library’s leaders and staff
to implement.
Methods
The consultants collected data through background document review,
interviews, focus groups, staff and public surveys, observation and analysis of building
systems. The data gathering provided information that helped the consultants to understand
the range of services offered by SFPL at the Main Library.
Findings
The study finds that the building is both a significant example of contemporary civic
architecture, and that serious operational problems are caused by the facility. The staff
experiences major problems providing public services and the public has difficulty
accessing services.
Findings and recommendations are presented in the following areas:
- Functional Design issues – related to how the building spaces are configured and their impact on functional and operational issues;
- Legibility Issues – how well users are able to navigate within the building to find materials and services;
- Capacity Issues – related to the building’s capacity to house materials, services and staff;
- Library Staff Issues- related to back of house library functions
- Facility Staff Issues - related to the building’s daily operations and maintenance.
Specific findings resulting from the data analysis are the following:
- Improvements to collection space are needed. In spite of the ample foot print and the provisions of compact shelving areas, there is not enough foot print to shelve the current collection. Some of the space problems result because of the number of openings in the floors, which reduces usable floor area.
- The "legibility" of the building should be improved. Users cannot find their way from the entry to service points or to collections to get to the materials or help they need. The on line catalog interface seems to contribute to these difficulties as does the shelving sequencing of the collection. All these factors contribute to making searching difficult for users.
Building signage is decorative, but does not provide any strategic way finding or materials location system that function with the online catalog.
- There are significant back of house operational issues. Staff encounters difficulties moving materials through the building and as a result, materials are damaged or are not as readily available for use as necessary in a library of this size.
The Technical Services Department is overcrowded and delivery of materials to them is destroying the service elevator.
- There are facility management issues that affect the ongoing operation and maintenance of the 367,000 SF facility. The public toilets are very difficult to maintain. The AV systems in the auditoriums are deficient. The loading dock does not work.
Recommendations
The Main Library building envelope is fixed by its Civic Center location; expansion
can only occur by reconfiguring interior floors or by using existing floor configurations
for different purposes. An important basic assumption on the part of the library is that
the library’s collection will not be reduced and that it will grow. This policy decision
leads to the overriding set of recommendations concerning ways to make room for the
collection, including reconfiguring floors, using Brooks Hall for archival and back
government documents, and finding other offsite locations for non public service
departments to release space in the Main Library for public services. Its finite capacity
should be reserved for public services, not back of house operational functions which
support the entire library system.
Brooks Hall, a former underground Exhibit Hall, should be used on a limited basis for
designated collections and services and should be staffed independently. The public should
access these collections directly from the Civic Center Plaza. Staff offices and reading
areas can be designed with special lighting and finishes to achieve a quality similar to
"First Stop" offices. In the consultants view, Brooks Hall presents some liabilities for
the library because it is essentially warehouse space which requires a tremendous
investment to bring it to a useable level for any other purpose than housing large
collection which requires minor staff support. Hence the recommendation that it be used
for the City Archive, which the library is charged with maintaining and will grow and other
special archives which are growing; and government documents older than ten years. These
types of collections require a great deal of shelving and the regular structural bays, as
well as the grade level floor slab make Brooks an ideal candidate. Limited facilities
storage for the Main Library and the Friends and Foundation book sale could also be
assigned to Brooks.
Under no circumstances should funds be spent to upgrade Brooks Hall exclusively for major
staff space or public space. The tendency to use Brooks for public collection overflow
should be resisted, otherwise it is likely that it will continue to house an accumulation
of uncatalogued material and equipment as it does today. Paging material from Brooks Hall
to public service points in the Main Library is a costly waste of staff resources.
If collections in storage on the lower level of the library are moved to Brooks Hall, the
remainder of the public collection should be shifted so that materials requiring greater
security or are less used move to vacated lower level storage space. The 1st and 2nd floors
should be dedicated to new and popular materials, the 3rd,4th and 5th floors should house
the remainder of the collection on open shelving, which is kept fully accessible. The 6th
floor and corner rooms on other floors should remain dedicated to their special collections,
with overflow made available in the Brooks Hall Archive.
The library’s current shelving as measured by the consultant team is 150,000 linear feet in
the main building and 45,357 linear feet in Brooks Hall. A good deal of this shelving is
compact shelving, housing material in the public collection on the 3rd, 4th and 5th floors
that has to be paged. Some of these materials may require greater security, but not all of it.
If floors are renovated in a similar manner to the recommendations in this report, the amount
of shelving can increase to 154, 242 linear feet in the Main Library ( a gain of 4, 188 linear
feet). This gain can be accomplished with the conversion of compact shelving to fixed shelving
allowing public access on the 3rd,4th and 5th floors. If Brooks Hall is renovated according to
the recommendations it will accommodate 109,410 linear feet ( a gain of 64, 054 linear feet).
Offsite space for non public services staff such as Personnel, Technical Services, Supplies and
Delivery, Automation, Finance, could be located in leased or permanent space. The existing
Federal Building in United Nations Plaza should be investigated to determine its ultimate
designation, as well as other leased space in the Civic Center. Another alternative would be to
locate offsite staff near a new or renovated branch. The site should be selected on the basis
of delivery requirements, parking and public transit requirements for staff. Offsite locations
should also take co-locations and partnerships with other libraries into consideration, such as
UCSF in Mission Bay, Hastings, the State Library, City College and other private colleges, to
save on administrative costs.
The following specific recommendations for facility changes to the Main Library are discussed
and diagrammed in the body of the report.
-
In order to improve capacity and provide space for collections:
- Some non-public service departments, which serve the system as a whole, need to move to another location which has parking, delivery and public transit access.
- Storage on the lower level can be freed up by moving archival materials and back government documents to a newly established city archive and back government documents center in Brooks Hall. An independent entry from the Plaza and attractive staff and reading rooms needed to be provided in Brooks Hall. (Note: a full underground floor was omitted from the library during the design phase which has greatly contributed to the space shortage.
Brooks Hall can serve as a replacement for that lost space.)
- Less used material from the public collection can then be moved to compact shelving and new fixed shelving on the lower level where it can efficiently be paged within the Main Library;
- The density of fixed shelving and number of user stations on floors can be increased. They are underutilized because of large ceremonial spaces.
-
In order to improve user access to the collection:
- Closed areas of compact shelving on the 3rd, 4th and 5th floors need to be opened for public access and replaced with fixed shelving so that the public can have access to these materials without the delay of having them paged.
- Signage needs to be improved throughout;
- Service points in the East Side of the 3rd,4th and 5th floors should be relocated for maximum visibility from stairs and elevators; and the number of service points needs to be consolidated to 2 per floor to allow staffing at all times.
- The 1st and 2nd floors need to be re-planned and staffed in order to clarify access to the building and to provide more room for the new book and browsing collection;
- The online catalog needs ongoing investment and improvement.
-
In order to improve materials management and back of house library operations:
- The main return and circulation sequence of activities needs to be consolidated in one desk to use staff effectively;
- Sorting needs to move directly adjacent to the intake function;
- Automated clearing of fines and overdue books needs to be accelerated;
- External book drops need to be redesigned or dismantled
- The loading dock needs to be more flexible for different sized loads.
-
In order to improve facilities management and maintenance:
- The maintenance budget needs to be prepared by a proactive team, including both the facilities manager and the finance director, which is committed to maintaining a major civic building;
- Facilities staff may need to be increased to maintain the building as it ages. Ongoing training and recruitment needs to be included in annual budgets;
- The Commission needs to support the facility improvement budgets not only to prevent deterioration, but also to support facility upgrades, with appropriate staff or on-call specialized consultants to manage the upgrades. The engineering staff has the time to operate and maintain facilities, but not to budget and manage renovation projects. Building maintenance and facilities renovation is two separate functions.
A facilities renovation/budgeting group needs to be established which has library facilities as its core focus.
Project Clusters and Costs
Proposed renovation consists of interior space planning changes requiring removal of non
bearing partitions, patching of ceilings and floors, relocation of lighting, relocation
of existing service desks, installation of shelving units. All exiting shelving and furniture
can be reused. Maintaining the design standards of the existing building is paramount.
Changes to the building’s mechanical, electrical systems require reconfiguration of the
distribution systems. The one structural change is the development of a bridge between
the west half of the 2nd floor to the Children’s Center and the grand stair, which will
require a light steel structure. This connection is intended eliminate the dead end at
the 2nd floor which confuses and frustrates users and staff. The connection will require
additional security and library staff. The proposed recommendations can be clustered into
six projects which are described in section four as follows:
Renovation Project 1 Lower Level
Classroom Addition and New Collection Shelving
$1,382,629.
Renovation Project 2 6th Floor Relocations
6th floor Relocations.
$798,719
Renovation Project 3 First and Second Floor
Part A Expand Browsing and Collections at 1st and 2nd Floors
$2,628,014
Part B Expand 2nd floor Collections and Access
$2,460,767
Part C First and Second Floor Desk Expansion
$3,138,582
Part D First Floor Rest Room Expansion
$930, 048
Renovation Project 4 Third and Fourth Floor Renovations
Part A 3rd and 4th Floor Service Desk Relocation and New Furniture Installation
$ 1,663,757
Part B Expand Collection Areas
$3,719,894
Renovation Project 5 Fifth Floor
Part A Relocate Periodical Shelving and Increase Reading Room Seating
$1,011,734
Brooks Hall Renovation
Complete the Brooks Hall renovation for archival collections, back government documents
and storage space.
$10,343,204
Benefits of Renovation
The library is currently full. The benefit of implementing the facility changes is to make
space for the collection and public services to allow the library to serve as the vital
information resource which San Francisco needs. The alternative appears to be reducing
the public collection to fit the building, or paging materials from a remote location.
In addition, on line public terminals at tables and carrels will be increased.
When materials are on open shelving, staff who currently page materials will be able to
provide increasingly effective public library services.
Clarifying the way finding in the building will also liberate staff from traffic control,
enhancing their ability to assist users with information retrieval.
Non-public departments will be able to serve the entire system more effectively and more
cost effectively because they will have adequate space and excellent delivery access.
Archival shelving and fixed shelving for back government documents will be provided in
Brooks Hall.
Project Closeout Items and Maintenance Trouble Spots
In addition to the facility recommendations made by the POE consultants, there are several
other open facility issues at the library resulting from the original design and construction
contract.
There appear to be a number of incomplete project closeout items. Once the building was
occupied, project closeout appears to have slowed. The Department of Public Works is in the
process of completing project closeout items, although the fact that there are open items
three years after the building was opened to the public is unusual. There should be no
additional cost for this work.
A number of conditions under warranty need to be addressed. There appear to be a number of
items for which the warranty period was extended for 5 years which do not function correctly.
The building engineers need to clarify these items and exercise these warranties with the
installers’ and manufacturers’ representatives. If they are unable to accomplish this, the
library needs to adopt an alternative approach before the warranties expire. There should be
no additional cost for this work, although staff time will be required.
A number of conditions which have proved to be difficult to maintain but which were designed,
constructed to current standards have been identified by the maintenance staff. To solve these
conditions, the library will need to hire architects, engineers and contractors to design and
construct repairs. The consultants and contractors may be hired from the city or from the
private sector. If the Library is using public funds for projects, the Library appears not to
have the authority to contract for design and construction services directly and will need to
have a Project Manager from DPW manage the work and retain services.
DPW currently holds a sum of approximately $3,000,000, the result of a settlement between the city,
the contractor and the design architects for dispersal on behalf of the Main Library. The Library
must determine the priority use of these funds. A further determination should be made as to whether
these funds are restricted to outstanding items from the original construction contract. The Library
needs to establish an internal project team and a reporting structures and measurable expectations
with DPW in order to come to closure on completing the building and use of discretionary funds.
|